Project Title Project Cost
Grand Street Widening - Fort to Grant $1,500,000
Norton Road - Summit to National 1,600,000
Walnut Lawn Right-Of-Way Acquisition/Construction Main to Kansas Expressway 3,000,000
Fremont Avenue at Republic Road 2,500,000
Grant Avenue - Norton to North City Limits 1,200,000
Jefferson Avenue at Sunshine Street 400,000
Total $10,200,000
Traditional Projects
Project Title Project Cost
Street Improvements, Traffic Signals & Sidewalks  
Metro/Safety Signs $100,000
Minor Neighborhood Improvement 600,000
Residential Street Stabilization 1,125,000
Road Concept Design 150,000
Shared Cost Agreement Project 900,000
Sidewalk Reconstruction/Ramp and School Sidewalk Program 1,750,000
Center City Parking/Streetscape Program
(Matched w/ CDBG Funds)
300,000
Traffic Signal Program 600,000
Sub-Total $5,525,000
Park Improvements  
Community Park/School Park and Greenway Development $400,000
Park Reforestation and Irrigation Program 125,000
Park Improvement Program 300,000
Park Land and School Park Acquisition 600,000
Sub-Total 1,425,000
Total $6,950,000
Unallocated Balance Estimate
1/4 Cent Sales Tax Estimated Revenues $21,000,000
Less 1/4 Cent CIP Continuation Projects 10,200,000
Less 1/4 Cent CIP Traditional Projects 6,950,000
Unallocated 2001 - 2004 1/4 Cent
CIP Revenues (Estimate)
$3,850,000
Projects
Project Title Project Cost
City Reforestation/Streetscape Landscape $1,200,000
Nathanael Greene Park Expansion/Development 100,000
Chesterfield Park Indoor/Outdoor Aquatics Center 3,000,000
McDaniel Park - Additional Land 500,000
Mobile Recreation Unit 100,000
Zoo Parking Lot Development - Phase I 280,000
Northview Senior Center 500,000
Skate Park Expansion $100,000
Total $5,780,000

planning and development; aerial photo of subdivision planning and development home

Contact Us

Busch Municipal Building
First Floor
840 Boonville Avenue
Springfield, MO 65802
Tel: 417.864.1615