PURPOSE:
To provide the minimum criteria necessary
to install a portable building.
DEFINITION:
Any prefabricated structure assembled off site and delivered to
the site as a complete unit or a building purchased in kit form
and assembled onsite, which can be moved without disassembly to
another location.
BULK, SETBACK AND SPACING REGULATIONS:
All portable building shall comply with the bulk, setback and spacing
regulations applicable in the zoning district in which they are
located and with the following additional regulations.
A. Portable buildings in residential districts shall be set back
a minimum of ten (10) feet from the rear lot lines. In all other
districts the portable building shall maintain the same rear yard
as is required for a principle structure located on the lot.
B. Portable buildings shall maintain the same side yard as is required
for the principal structure located on the same lot.
C. Portable structures shall otherwise comply with the bulk height
regulations applicable in the district in which they are located.
D. No portable structure shall be permitted in any required front
yard.
E. On corner lots, portable structures must setback half the setback
distance of the adjacent structure facing the side street.
F. All portable structures used for temporary vending as established
in G.O. 4927 shall be excluded from these requirements.
INSTALLATION REQUIREMENTS:
If the portable structure has a total area exceeding 100 square
feet the following installation requirements shall apply.
A. A building permit shall be required.
B. A site plan showing the principle structures and the proposed
location of the portable structure shall be submitted with the building
permit application.
C. The structure shall be set on a permanent foundation or piers
capable of carrying and distributing all imposed loads. The structure
also shall be provided with a means to prevent wind uplift. This
may be accomplished with trailer tie downs or permanently attached
to the foundation or piers. A sketch showing how these items will
be constructed shall be submitted for review.
D. The foundation shall bear on undisturbed soil a minimum of two
(2) feet below the finished grade.
E. All portable structures used for nonresidential uses shall be
certified by a third party that the structural system meets the
loading criteria set forth in the building code. This letter of
certification shall bear the seal of a registered Missouri Engineer
and shall be submitted with the building application.
|