Project Title | Project Cost |
---|---|
Public/Private Shared Cost & Economic Development | $1,400,000 |
Street Concept Design | $250,000 |
Sidewalk/Curb/Ramp Reconstruction | $2,250,000 |
School Sidewalk Program | $1,000,000 |
Metro Safety Signs & Markings (includes bike routes) | $900,000 |
Street Stabilization & Major Repaving | $3,000,000 |
Traffic Signal/Traffic Calming Program | $1,200,000 |
Neighborhood Improvements (pothole funds) | $600,000 |
Center City Development | $1,000,000 |
Reforestation & Landscaping Improvements | $750,000 |
Total | $12,350,000 |
Project Title | Project Cost |
---|---|
Primrose & Campbell Intersection | $2,750,000 |
Republic Road (Campbell to Kansas) | $2,950,000 |
Mt. Vernon Suburban to Orchard Crest | $2,250,000 |
Design & Partial Right-of-Way (ROW) | |
Packer/Kearney Intersection & 700 ft North | $500,000 |
Primrose - South to Kings | $100,000 |
Republic Road (JRF Bridge to Campbell) | $100,000 |
Stormwater Permit Compliance (water quality) & Flood Control | $4,500,000 |
Total | $13,150,000 |