Construction Forecast
The schedule below is an estimated timeline of Public Works projects coming forward for bid or construction.
View current contractor bid notifications.
Est. Bid Date | Project | Description | Target Start Date | Est. Duration | Division | Project Manager | Design Consultant | Funding Source |
---|---|---|---|---|---|---|---|---|
Summer 2022 | SWTP Plant 2 Rehabilitation | Misc. aeration basin and headworks rehabilitation improvements | Fall 2022 | 1 year | Environmental Services Wastewater Treatment | A. Busick | Burns & McDonnell | Sewer Fund Balance Reserves |
Spring 2022 | ADA Improvements | ADA for Overlay Project | Fall 2022 | 3 months | Transportation Engineering | A. Nelson | Toth | 1/4-Cent, STBG |
April 2022 (through MoDOT) | Republic Road Widening | Widen Republic Road to 5 lanes (Fairview to Chase) | Summer 2022 | TBD | MoDOT | A. Haase | CMT | STBG, 1/8-cent |
On hold for additional funding | Jefferson Avenue Footbridge | Rehabilitate Jefferson Avenue Footbridge | On hold for additional funding. | 6 months | Transportation Engineering | N. Edelman | Great River Engineering | STBG, 1/4-cent, 1/8-cent, community donations |
Summer 2022 | Grant and Norton Stormwater Project | Stormwater Infrastructure improvements extending from Norton Road to Evergreen Street. | Fall 2022 | 6 months | Stormwater Engineering | J. Codichini | Olsson | LPT, 1/4-cent |
Spring 2022 | Delaware Stormwater Improvements from Talmage to North | Stormwater infrastructure improvements along Delaware Avenue from Talmage St. to North Street. | Summer 2022 | 3 Months | Stormwater Engineering | Z. Mills | Crawford, Murphy, and Tilly | Minor Neighborhood Improvement Program |
Spring 2022 | Hampton from Seminole to Cherokee | Stormwater Infrastructure Improvements | Summer 2022 | 6 Months | Stormwater Engineering | K. Preston | Toth and Associates | LPT, 1/4-cent |
Spring 2022 | Jordan Creek Regional Detention B6 at Chestnut | Stormwater Infrastructure Improvements | Winter 2022 (Q4) | 9 Months | Stormwater Engineering | K. Preston | HDR Engineering, Inc. | LPT |
Winter 2022 (Q4) | National Ave. & Division St. Intersection | Upgrade signals, intersection alignment improvements | Winter 2023 (Q1) | Transportation Engineering | Z. Butcher | CMT | 1/8-cent | |
Winter 2022 (Q1) | Division Street Reconstruction | New pavement, curb and gutter, sidewalk and stormwater infrastructure (National to Glenstone) | May 2022 | Transportation Engineering | Z. Butcher | CMT | 1/4-cent | |
Spring 2022 | Battlefield & Luster Signal Improvement | Signal replacement and sidewalk reconstruction | Summer 2022 | 60 days | Transportation Management | J. Saliba | ||
Summer 2022 | Galloway Street Widening | Widen Galloway Street (Luster to Lone Pine) to 3 lanes | Fall 2022 | 12 months | Transportation Engineering | N. Edelman | HDR | 1/4-cent & Governor's Cost Share |
Spring 2022 | Jefferson Ave. Streetscape | Streetscape improvements on the east side of Jefferson between Walnut and St. Louis including new traffic signals. | Summer 2022 | Transportation Engineering | A. Nelson | Olsson | 1/4-cent | |
Winter/Spring 2022 | Landfill Office Building | Renovation of the existing office building and an addition on the east side of the existing building. | Spring/Summer 2022 | 16 months | Facilities Design & Construction | L. Morrow | BRP Architects | City Solid Waste Fund Balance Reserves |
Winter/Spring 2022 | Police Headquarters Carpet Replacement | Replacement of all carpet and other related improvements. | Spring/Summer 2022 | 6 months | Facilities Design & Construction | K. Woodside | In-house | General Fund |
Summer 2022 | Replacement Fire Station #7 | Demolition of the existing station and construction of a new two-bay, one story Fire Station and other site improvements. | Fall 2022 | 12 months | Facilities Design & Construction | L. Morrow | Esterly Schneider | LPT, Bond 1 |
Summer 2022 | Bengsch Building Mechanical System Replacement | Complete replacement of the facility's mechanical system. | Fall 2022 | 6 months | Facility Design & Construction | L. Morrow | TBD | Health Department |
Summer 2022 | Commercial Street Gateway Signage | Gateway signage/entrances to the Historic C-Street District | Summer 2022 | 6 months | Facilities Design & Construction | K. Woodside | BPR Architects | C-Street TIFF |
Winter 2024 | Historic City Hall Renovation | Renovation of the Historic Structure to provide accessible circulation and facilities, improved HVAC and Electrical systems, and modern office spaces for various City Departments. | Spring 2024 | 18 months | Facility Design & Construction | J. Swan | TBD | LPT, Bond 2 |
Spring 2023 | Battlefield & Lone Pine | Intersection, stormwater, sidewalk improvements and signal upgrades | Fall 2023 | Transportation Engineering | N. Edelman | HDR | 1/4-cent | |
Spring 2023 | National Avenue Lane Addition (Walnut Lawn to Battlefield) | Lane addition on southbound lanes including stormwater, sidewalk/trail improvements | 2023 | Transportation Engineering | N. Edelman | CJW | 1/8-cent | |
2023 | Walnut Lawn & Campbell Intersection | Intersection Improvements including stormwater and sidewalk improvements. | 2024 | TBD | Transportation Engineering | N. Edelman | CJW | 1/8-cent |
2023 | Walnut St. Bridge | Bridge replacement | 2024 | 12 months | Transportation Engineering | A. Haase | CMT | 1/4-cent |
Winter 2023 (Q1) | Police Headquarters Roof Replacement | Remove existing coal tar roof and replace with modified bitumous roof | Spring 2023 | 8 months | Facility Design & Construction | K. Diehls | TBD | LPT |
Summer 2023 | Fire Station #3 Improvements | Various facility improvements such as new windows, mechanical and electrical upgrades, and parking lot repairs | Fall 2023 | 7 months | Facility Design & Construction | L. Morrow | TBD | LPT |
Summer 2024 | Animal Shelter | A new 12,000 sq. ft. animal shelter facility primarily for feline and canine temporary housing and support spaces for animal care and staff. | Fall 2025 | 18 months | Facilities Design & Construction | C. Holland | TBD | LPT, Bond 2 |
2024 | Fire Station #9 Improvements | Various facility improvements such as roof replacement, mechanical and electrical upgrades, and parking lot repairs. | 2024 | 9 months | Facility Design & Construction | K. Diehls | TBD | LPT |