Division Street Reconstruction

DivisionSt_Reconstruction_web
Completed as promised banner-01

Reconstruction of Division Street between National Avenue and Glenstone Avenue included the DJI_0009complete rebuild of the roadway including new pavement, curb and gutter as well as stormwater drainage improvements. A new sidewalk was constructed along the north side of the roadway and a multi-use path along the south side. Gas and water utility renewals were conducted through a cost-share agreement with City Utilities.  

Construction was completed on-time within the one-year expected project duration and cost approximately $4.7 million, funded through the 1/4-cent Capital Improvement and 1/8-cent Transportation sales taxes. 

TRAFFIC IMPACTS: 

Beginning June 21, 2023, the roadway reopened to two-way traffic between National and Glenstone avenue as crews began to wrap up major construction on the project. 


PROJECT DETAILS:

Construction Began: 
July 2022

Construction Complete:
July 2023

Anticipated Duration: 1 year

Contractor:  Hartman & Co.

Engineering Design: Crawford, Murphy, and Tilly (CMT)

Construction Cost:
$4.7 million

Funding Source: 

  • 1/4-cent Capital Improvement Sales Tax
  • 1/8-cent Transportation Sales Tax

Project Manager:
King Coltrin
[email protected]