Reconstruction of Division Street between National Avenue and Glenstone Avenue included the
complete rebuild of the roadway including new pavement, curb and gutter as well as stormwater drainage improvements. A new sidewalk was constructed along the north side of the roadway and a multi-use path along the south side. Gas and water utility renewals were conducted through a cost-share agreement with City Utilities.
Construction was completed on-time within the one-year expected project duration and cost approximately $4.7 million, funded through the 1/4-cent Capital Improvement and 1/8-cent Transportation sales taxes.
TRAFFIC IMPACTS:
Beginning June 21, 2023, the roadway reopened to two-way traffic between National and Glenstone avenue as crews began to wrap up major construction on the project.