FOR IMMEDIATE RELEASE
A portion of Charleston Avenue, between Carleton Street and Briar Street, will be closed for two weeks Nov. 16-30 as part of the Ravenwood South subdivision phase 1 stormwater project.
The project includes stormwater improvements to stabilize the channel and reduce flooding in the Ravenwood South subdivision.
Access to all properties will remain open throughout construction, but traffic will be closed to through traffic along this portion of Charleston.
This project, to be completed spring 2016, is estimated to cost $700,000 and is funded through the 1/4-cent Capital Improvement Sales Tax.
The contractor on the project is Flat Creek Excavation.
# # #
For more information, please contact Public Works project manager Colten Harris at 864-1990.